Commercial solar EPC since 2014

Kern County / Tulare County / Kings County / Fresno County

(661) 555-0183

Built and metered

Case files, not a photo gallery

Every project below carries the array size in kW DC, the inverter capacity in kW AC, modelled annual production in kWh and what the design had to work around. All figures are samples for this demonstration site.

Case files
6
Combined array
7.37 MW DC
Modelled output
12.9 GWh / yr
Counties
Kern, Tulare, Kings
A completed ground-mount solar field with access road

All case files

01 · Cold storage and packing · Delano, CA

Kern Ridge Packing

A grape packing and cold storage operation whose annual demand charge was being set by a single week of intake in late July. The array covers the daytime refrigeration load; the battery exists purely to hold the monthly peak down during pull-down.

Array
842kW DC
Inverters
700kW AC
Annual
1,412MWh
Offset
63%
PTO
March 2025
Open case file

02 · Water and municipal · Buttonwillow, CA

Buttonwillow Water District

A 2.35 MW DC tracker field on district-owned basin margin land, serving three pumping meters. The district shifted its own load by filling storage reservoirs in the generation window instead of buying a battery.

Array
2,350kW DC
Inverters
1,900kW AC
Annual
4,230MWh
Offset
71%
PTO
September 2024
Open case file

03 · Education · Shafter, CA

Shafter Unified canopies

Solar canopies across three campus lots, built in two summer windows. The structures carry the array, the lot lighting and the conduit for a future electric bus fleet.

Array
614kW DC
Inverters
500kW AC
Annual
1,038MWh
Offset
58%
PTO
November 2024
Open case file

04 · Food and beverage processing · Tulare, CA

Tulare dairy processing

A split roof-and-yard system for a dairy processor running 24 hours through the flush. A compressed-air survey done during the audit removed enough load to shrink the array before it was designed.

Array
1,480kW DC
Inverters
1,250kW AC
Annual
2,590MWh
Offset
44%
PTO
June 2025
Open case file

05 · Agriculture and irrigation · Wasco, CA

Wasco almond ranch

A fixed-tilt field on a fallowed corner serving two deep-well pump meters. The array is aimed 22 degrees west of due south because that is where the irrigation day actually sits.

Array
1,120kW DC
Inverters
900kW AC
Annual
2,010MWh
Offset
78%
PTO
February 2025
Open case file

06 · Warehousing and distribution · Bakersfield, CA

Bakersfield distribution centre

A 960 kW roof array deliberately sized below the available roof area, matched to a load that is about to grow as the yard tractor fleet electrifies.

Array
960kW DC
Inverters
800kW AC
Annual
1,620MWh
Offset
52%
PTO
August 2025
Open case file

Your project would be number seven

Bring us the interval data and the building. We will tell you what fits, what it produces, and where the demand charge actually comes from.

CSLB #1071482 (sample). Prevailing wage on public works. Engineers answer, not a call centre.

Cookie preferences

Choose which cookies you allow. You can change this at any time from the link in the footer.