Delivery

Eight stages, one accountable party

Engineer, procure, construct. One contract, one schedule, one party answering for it. Here is the sequence, the typical week ranges and who owns each gate.

Delivery model
Full EPC
Stages
Eight
Typical rooftop
26 to 34 weeks
Client gates
Two design reviews
Engineers reviewing drawings on a construction site

Sequence

From interval data to permission to operate

  1. 01

    Interval data and audit

    Weeks 1 to 3

    Twelve months of 15-minute data pulled, load shape built, peak events attributed to equipment, tariff modelled.

  2. 02

    Site survey

    Weeks 2 to 4

    Roof, yard, switchgear and service. Drone survey, moisture scan where relevant, structural as-builts collected.

  3. 03

    Engineering and basis of design

    Weeks 4 to 8

    Layout, yield model, structural calculations, single line, protection scheme and the storage sizing if any.

  4. 04

    Permitting and interconnection

    Weeks 6 to 22

    AHJ plan check and the Rule 21 path, filed in parallel. This is where the schedule is won or lost.

  5. 05

    Procurement

    Weeks 8 to 16

    Modules, inverters, racking and switchgear ordered against lead times, staged in our own yards.

  6. 06

    Construction

    Weeks 16 to 28

    Civil, structural, racking, modules, DC and AC electrical, phased around your operating hours.

  7. 07

    Commissioning

    Weeks 26 to 30

    IV curve traces on every string, insulation resistance, protection settings, inverter configuration and the baseline report.

  8. 08

    PTO and handover

    Weeks 28 to 32

    Utility permission to operate, monitoring credentials, as-builts, warranty registry and the O&M calendar.

Stages overlap deliberately. Permitting and interconnection start while engineering is still running, and procurement starts before permits land where lead times demand it.

Schedule

What we run in parallel, and why it matters

The utility interconnection path and the building permit path are separate queues run by separate organisations. Neither depends on the other. Running them sequentially, which is common, adds months for no engineering reason at all.

We file both in the same week. If the plan check takes twelve weeks and the utility path takes sixteen, the project spends sixteen weeks in review rather than twenty-eight.

Procurement is the other overlap. Switchgear and transformers have long and volatile lead times, so on projects where those items are critical we place orders against the approved basis of design rather than waiting for a stamped permit.

The two gates that need you

  • Basis of design review, around week 6. System size in kW DC, modelled kWh, layout, storage sizing and the cost range. Changes here are cheap.
  • Construction readiness review, around week 15. Final layout, schedule, site access, shutdown windows and phasing. Changes here are not cheap.

The long pole

Interconnection is where schedules go to die

Every stage above is ours to control except one. The utility process has its own queue, its own screens and its own calendar, and it usually sets the energisation date.

Read the eight interconnection gates

Answers

Delivery: questions

Not covered here? Our engineers answer directly, not through a call centre.

Ask a question(661) 555-0183

Engineer, procure, construct. We do the engineering, buy the equipment and build the system, under one contract with one party accountable. The alternative is a designer, a supplier and an installer pointing at each other when something does not line up.

Electrical, racking and commissioning are our own crews. Civil works, structural steel erection, crane work and roofing are subcontracted to firms we use repeatedly, under our supervision and our schedule.

In almost every case. We phase the work around operating hours and, for seasonal facilities, around the campaign. The one unavoidable interruption is the electrical tie-in, usually a single day and usually at a weekend.

Sign an interval-data release, give us site access, nominate one decision maker, and attend two design reviews. Everything else is ours. The single most useful thing a client does is respond quickly at the two review gates.

Monitoring credentials, the commissioning report with string-level IV traces, as-built drawings, the equipment serial registry, warranty documents and the O&M calendar. Then the first performance review at 90 days.

Bring us the bill before you bring us the roof

Every project starts with twelve months of interval data and a load shape. The array comes after that, sized to what you actually use.