Bakersfield distribution centre

A 960 kW roof array deliberately sized below the available roof area, matched to a load that is about to grow as the yard tractor fleet electrifies.

Array
960 kW DC
Inverters
800 kW AC
Annual output
1,620 MWh
Permission to operate
August 2025
Bakersfield distribution centre installation

Specification

The numbers on the record

All values are samples for this demonstration site.
ClientValley Route Logistics
LocationBakersfield, CA
Array rating960 kW DC
Inverter rating800 kW AC (DC to AC ratio 1.20)
Modules1,745 at 550 W
StructureBallasted rooftop, east-west rows at 5 degrees
StorageNone; 8 yard-tractor charging ports installed
Modelled annual production1,620,000 kWh
Specific yield1,688 kWh per kW DC per year
Load offset52 percent
Construction window10 weeks
Permission to operateAugust 2025

What made it hard

The constraints

  • The roof could physically carry more than 2 MW while the building only drew a few hundred kW during the day.
  • An electric yard-tractor pilot was eighteen months out and undefined, but it would change the load shape completely.
  • A leased building, which meant landlord consent and a lease term shorter than the array's life.

What we did about it

The approach

  • Array sized to daytime load plus the modelled first phase of fleet charging, not to the roof, keeping exported energy to a small share of output.
  • East-west rows at 5 degrees to maximise kW on the available structure within the dead-load limit, accepting slightly lower specific yield per kW.
  • Switchgear and conduit sized for sixteen charging ports; eight installed, eight stubbed with pull boxes at the yard.
  • Structured as a power purchase agreement so the tenant pays per kWh and the lease term question stops being a blocker.

Result

Outcome

System size
960 kW DC / 800 kW AC
Modelled annual output
1,620,000 kWh
Load offset today
52 percent
Exported share
Under 9 percent of generation
Charging capacity
8 ports live, 16 stubbed
Bakersfield distribution centre detailBakersfield distribution centre, Bakersfield, CA

Everyone else quoted the whole roof. SunHarvest quoted the load we have and the fleet we are actually buying.

Tobias ReinhardtRegional Facilities Lead, Valley Route Logistics

Bring us the bill before you bring us the roof

Every project starts with twelve months of interval data and a load shape. The array comes after that, sized to what you actually use.